The approved hotel refurbishment is currently expected to begin in summer 2027. Subject to planning approval, we intend to coordinate the proposed spa works concurrently with those works. This will help to limit the overall period of disruption to our neighbours.
The Construction Management Plan
We are consulting on a draft Construction Management Plan (CMP) for the proposed spa. This will explain how the works would be organised, including working hours, deliveries, measures to reduce noise, dust and vibration, and how we would keep you informed. Your feedback will help shape the plan before it is submitted to Westminster City Council for review and approval.
Proposed site arrangements
The below map shows the proposed construction logistics plan, including loading bay, conveyor system for removing building waste, and vehicle and pedestrian routes. This plan would be agreed with Westminster City Council and relevant highways authorities.
How long the spa works could take
Our draft timetable allows:
8 weeks for the contractor to prepare before work starts on site
Up to 42 weeks to build the basement structure - this would happen concurrently with the rest of the already consented restoration works
25 weeks to install the spa equipment and finish the interior
4 weeks for final checks and completion.
These early estimates comprise around 71 weeks on site, plus preparation time. The contractor would confirm the timetable, including how the spa and hotel works would fit together, as well as their start and completion dates. It is estimated that all work would be complete and the hotel reopen in Autumn 2029.
You can read more about how we would keep the site safe and how we would manage traffic and pedestrian access on our Construction Management Boards.
Keeping you informed
We plan to keep neighbours up to date with regular emails and newsletters, explaining upcoming works, likely disruption and any timetable changes. We also propose resident meetings with our contractor every three months, with a written record of discussions and agreed actions.
We would normally give at least five working days’ notice of particularly disruptive works, including any approved works outside of normal working hours. We would let affected neighbours know about emergency works or unexpected changes as soon as possible.